Self-Optimization

RushTI learns from each run. It tracks how long each TI process takes and reorders tasks for better parallelization using your chosen scheduling algorithm.


How It Works

  1. Run your workflow — RushTI records how long each task took in a local SQLite database.
  2. Build a performance picture — After several runs, RushTI calculates a weighted average duration for each task (recent runs count more).
  3. Opt in to optimization — Choose a scheduling algorithm via --optimize on the CLI or optimization_algorithm in a JSON task file. RushTI reorders ready tasks using EWMA estimates.

The result: better worker utilization and shorter total execution time — without changing your task files.


Scheduling Algorithms

RushTI supports two scheduling algorithms. The right choice depends on your workload:

Algorithm Sort Order Best For
longest_first Longest tasks start first Independent workloads with varied task durations. Starts expensive tasks early so short tasks fill gaps.
shortest_first Shortest tasks start first Shared-resource TM1 workloads where concurrent heavy tasks cause contention (memory, threads, write locks).

When to Use Which Algorithm

  • longest_first — Classic bin-packing heuristic. Works well when tasks are independent and the TM1 server has headroom. Ideal for read-heavy extract workflows targeting multiple instances.
  • shortest_first — Reduces peak resource pressure by completing quick tasks first, lowering the number of concurrent heavy tasks. Ideal for write-heavy loads against a single TM1 instance.

Not sure? Start with shortest_first

Most TM1 workloads involve shared server resources. shortest_first is a safer default for typical Planning Analytics environments.


Enable Optimization

Optimization is off by default. You opt in explicitly per-run or per-taskfile.

Via CLI

# Shortest-first scheduling (good for shared-resource TM1 workloads)
rushti run --tasks daily-refresh.json --max-workers 20 --optimize shortest_first

# Longest-first scheduling (good for independent tasks with varied durations)
rushti run --tasks daily-refresh.json --max-workers 20 --optimize longest_first

Via JSON Task File

Set a default algorithm in the task file's settings section:

{
  "settings": {
    "optimization_algorithm": "shortest_first"
  }
}

CLI --optimize overrides the JSON setting. Omitting both means no optimization.

EWMA Tuning (settings.ini)

The EWMA parameters that control how runtime estimates are calculated live in settings.ini. These are system-wide and rarely changed:

[stats]
enabled = true
retention_days = 90

[optimization]
lookback_runs = 10
min_samples = 3

What's happening under the hood

When multiple tasks are ready to execute (i.e., all their predecessors have completed), RushTI sorts them by estimated runtime using the chosen algorithm before assigning them to workers. Dependencies are never changed; only the order among independent, ready tasks is affected.

Requirements

  • [stats] enabled = true — Optimization needs historical data. Without stats, there's nothing to learn from.
  • At least min_samples runs — Tasks with fewer runs than min_samples use a default estimate and are placed after tasks with known durations.

Before and After

Consider a simple workflow with six independent tasks and two workers:

Before optimization (random order):

Worker 1: [Short 2s] [Short 3s] [Long 30s] ──────── Total: 35s
Worker 2: [Short 1s] [Long 25s] ───── [Short 4s]    Total: 30s
                                              Overall: 35s

Worker 1 finishes early tasks quickly, then hits the long task last. Meanwhile Worker 2 sits idle waiting.

After optimization (longest first):

Worker 1: [Long 30s] ──────────── [Short 2s] [Short 1s]  Total: 33s
Worker 2: [Long 25s] ───── [Short 4s] [Short 3s]         Total: 32s
                                                   Overall: 33s

Both workers stay busy throughout. The total time drops because long tasks start immediately and short tasks fill in the remaining gaps.

Real-World Gains

The improvement depends on how unbalanced your tasks are. Workflows with a mix of 5-second and 5-minute tasks see the biggest gains. Workflows where all tasks take roughly the same time see less benefit.


Configuration

Setting Location Default Description
--optimize CLI (none) Scheduling algorithm: longest_first or shortest_first. No flag = no optimization.
optimization_algorithm JSON taskfile (none) Per-taskfile default algorithm. Overridden by CLI --optimize.
lookback_runs settings.ini 10 Number of recent runs to analyze for EWMA estimates
min_samples settings.ini 3 Minimum successful runs before optimization kicks in
cache_duration_hours settings.ini 24 How long to cache duration estimates between runs
time_of_day_weighting settings.ini false Weight runs at similar times of day higher (disables caching)

How Duration Estimates Work (EWMA)

RushTI uses EWMA (Exponentially Weighted Moving Average) to estimate task durations:

  • Recent runs matter more. If a process used to take 10 seconds but now takes 20 seconds (because data volumes grew), the estimate adjusts toward 20 seconds.
  • Old outliers fade away. A one-time spike from a server hiccup does not permanently distort the estimate.
  • The smoothing factor (alpha) is 0.3. Each new run contributes 30% to the estimate, and the accumulated history contributes 70%.

For most TM1 environments, the default alpha works well. If your process durations change rapidly (for example, during a data migration), see Performance Tuning for EWMA tuning details.

Time-of-Day Weighting

Some TI processes run faster at night when the server is idle and slower during business hours. Enable time_of_day_weighting to give more weight to runs that happened at a similar time of day:

[optimization]
time_of_day_weighting = true

Note

When time_of_day_weighting is enabled, caching is disabled — RushTI recalculates estimates fresh each run to account for the current time of day.

Choosing min_samples

Workflow Type Recommended min_samples Reason
Stable daily ETL 3 Durations are consistent
Variable workloads 5-10 Need more data points to smooth out variation
Seasonal processes 10-20 Data volumes change significantly

Manual Analysis (Optional)

In addition to automatic optimization, RushTI includes a manual analysis tool for generating reports and optimized task files:

rushti stats analyze \
  --workflow daily-refresh \
  --tasks daily-refresh.json \
  --output daily-refresh-optimized.json

This reads your execution history, calculates EWMA estimates, and writes a new task file with tasks reordered for optimal execution. This is useful for:

  • Reviewing performance — see which tasks are getting slower or faster
  • Sharing an optimized file — distribute a pre-optimized task file to a team that hasn't enabled automatic optimization
  • Auditing — compare the original and optimized order to understand what changed

What the Report Shows

Field Description
task_id The task identifier from your task file
avg_duration Simple average across all analyzed runs
ewma_duration Weighted average (recent runs matter more)
min_duration Fastest observed execution
max_duration Slowest observed execution
run_count Number of runs analyzed

Reading the results:

  • EWMA < Average — The task is getting faster over time
  • EWMA > Average — The task is getting slower (investigate data volumes or TI process performance)
  • EWMA ≈ Average — Stable performance

TM1 Integration

If you have TM1 Integration enabled (push_results = true), optimization data is also visible in TM1. The rushti cube stores task durations for every run, so you can build Planning Analytics dashboards that show:

  • Which tasks are getting slower over time
  • Which workflows benefit most from optimization
  • Historical duration trends per TI process
  • Success rates and failure patterns

Frequently Asked Questions

Does optimization change my task dependencies?

No. Optimization only reorders tasks that are independent of each other (tasks at the same depth in the DAG with no shared predecessors). Your dependency chains are never modified.

How many runs do I need before optimization helps?

At least 3 runs (the min_samples default). With fewer runs, the duration estimates are unreliable and RushTI skips optimization for those tasks. For best results, aim for 5-10 runs.

Which algorithm should I use?

  • shortest_first — Best for most TM1 workloads, especially write-heavy processes against a single TM1 instance. Reduces peak resource contention.
  • longest_first — Best for independent, read-heavy workloads spread across multiple TM1 instances. Classic bin-packing heuristic.

When in doubt, start with shortest_first.

Can I set a default algorithm per task file?

Yes. Add "optimization_algorithm" to the JSON task file's settings section. The CLI --optimize flag overrides this value at runtime:

{
  "settings": {
    "optimization_algorithm": "shortest_first"
  }
}

Can I optimize a TXT task file?

Yes. Optimization works with both JSON and TXT task files. Use --optimize <algorithm> on the CLI. The stats analyze command also works with both formats.

What if I add new tasks to the workflow?

New tasks will not have historical duration data, so RushTI treats them as unknown and places them after tasks with known durations. After a few runs, the new tasks accumulate enough data to be included in optimization.

Can I use optimization with exclusive mode?

Yes. Optimization and exclusive mode are independent features:

rushti run --tasks daily-refresh.json --max-workers 4 --exclusive --optimize shortest_first

Best Practices

  1. Enable stats from the start. Even if you do not plan to optimize immediately, having historical data ready is valuable. It costs almost nothing in overhead.

  2. Let it learn. After enabling optimization, the first few runs build the performance picture. Gains become visible after min_samples runs.

  3. Combine with manual tuning. Optimization reorders tasks but does not make individual TI processes faster. If the stats show a process taking 5 minutes, consider optimizing the TI process itself (better MDX, fewer loops, targeted data clears).

  4. Use time_of_day_weighting for mixed schedules. If the same workflow runs both during business hours and overnight, enable time-of-day weighting to account for load differences.